The Urbana, Chakan
Lapsed
by Intercontinental Infrastructure Limited. Chakan, Pune 410501. View on Google Maps
- Launched
- 2 years 4 months originally promised
- Possession date (MahaRERA)
- 7 months ago. No further extension recordedExtended by 6 years 3 months (originally December 2019). What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 110 of 11992% booked
Project facts
| 1 BHK | 83 |
|---|---|
| 2 BHK | 36 |
| Total units | 119 |
| Buildings | 1 |
| Land | 3.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 14 |
Since Dec 2025: booked 59 → 110 · total units 132 → 119
Compared with 6 similar projects in PIN 410501
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 4 mths | 3 yrs 1 mth |
| Possession date extended | By 6 years 3 months | 6 of 6 |
| Possession date passed | Yes, due March 2026 | 2 ready to move; 3 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 92% | 46% |
| Complaints on MahaRERA (filed by or against the builder) | 14 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Amrutvel | August 2017 | March 2025 | 100% | 58 of 125 booked (46%) |
| Urja Cornerstone Building 2 | August 2017 | December 2020 | 100% | 34 of 98 booked (35%) |
| Urban County A & B Wing | August 2017 | October 2023 | 100% | 86 of 95 booked (91%) |
| Laxmi Vishwa | August 2017 | December 2026 | 50% | 54 of 178 booked (30%) |
| Phase IV - K1 and L1 Buildings | August 2017 | December 2025 | 100% | All 176 units booked |
| Phase I - Buildings A, A1, P and S,T,U Combined wing | August 2017 | December 2030 | 100% | 113 of 245 booked (46%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 110 | |
| 100% | 100% | 25% | 59 | |
| 100% | 100% | 20% | 59 | |
| 100% | 95% | 15% | 49 | |
| 100% | 30% | 0% | 15 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
The Urbana (MahaRERA P52100011910) is a residential project by Intercontinental Infrastructure Limited in Chakan, Pune 410501. It was launched in August 2017. It has 119 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2026, after an extension of 6 years 3 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete. MahaRERA records do not show it as ready to move in.
110 of its 119 units are booked (92%). Since the December 2025 update, 51 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.