Skip to main content
← Back

Kohinoor Westview Reserve, Punawale

by Goldway Realty Private Limited. Punawale, Pune 411033. View on Google Maps

Launched
5 years 11 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
80%Mid-constructionAverage across 5 buildings
Units booked
718 of 79490% booked

Project facts

1 BHK85
2 BHK445
3 BHK256
Other units (shops, offices or not given by type)8
Total units794
Buildings5
Land4.3 acres
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 713 → 718 · complaints 0 → 2

Share on WhatsApp

Compared with 5 similar projects in PIN 411033

Projects with 350–1,600 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 11 mths6 yrs 3 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)December 2028December 2028
Concrete structure (RCC) complete80%83%
Share of units booked90%68%
Complaints on MahaRERA (filed by or against the builder)21

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 9 months of the promised 5 years 11 months have passed
Concrete structure (RCC) 80% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 76%Jun 2024: Excavation 80%Dec 2024: Excavation 80%Jun 2025: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 73%Dec 2024: Concrete structure (RCC) 80%Jun 2025: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%80%0%718
80%80%0%713
80%80%0%635
80%73%0%577
76%0%0%395

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Kohinoor Westview Reserve (MahaRERA P52100048589) is a residential project by Goldway Realty Private Limited in Punawale, Pune 411033. It was launched in January 2023. It has 794 units in 5 buildings: 786 homes (1, 2 & 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 5 buildings: excavation 80% complete, structure (RCC) 80% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

718 of its 794 units are booked (90%). Since the December 2025 update, 5 more units have been booked.

Kohinoor's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA48
Completed without extending the possession date13
Completed after an extension, or lapsed10
Under construction25
Possession date extended by the builder8
Typical time from launch to 100% structure3 years 3 months
Complaints on MahaRERA, all Kohinoor projects52 (19 of 48 projects)

See all Kohinoor projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100048589.Check it on MahaRERA (P52100048589)All projects in Tathawade, Punawale, Jambhe