Elegance Vega, Baner
by Elegance Landmarks. Baner, Pune 411045. View on Google Maps
- Launched
- 3 years 4 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 6 months (originally June 2026). Why possession dates change
- Concrete structure (RCC)
- 98%Mid-constructionAverage across 2 buildings
- Units booked
- 70 of 7495% booked
Project facts
| 2 BHK | 63 |
|---|---|
| Other units (shops, offices or not given by type) | 11 |
| Total units | 74 |
| Buildings | 2 |
| Land | 0.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 52 → 70 · structure 0% → 98% · final finishes 0% → 35% · possession date June 2026 → December 2026
Compared with 6 similar projects in PIN 411045
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | By 6 months | 3 of 6 |
| Possession date (MahaRERA) | December 2026 | May 2027 |
| Concrete structure (RCC) complete | 98% | 75% |
| Share of units booked | 95% | 82% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nancy Hillview A-2 | January 2023 | September 2027 | 100% | All 84 units booked |
| 17 East | January 2023 | September 2026 | 50% | 29 of 36 booked (81%) |
| Estrella 45 | January 2023 | December 2026 | 100% | 26 of 31 booked (84%) |
| The Midas Residences Phase 2 | March 2023 | December 2029 | 0% | 71 of 98 booked (72%) |
| The Midas Residences Phase 3 | April 2023 | December 2029 | 0% | 8 of 47 booked (17%) |
| La Moda | December 2022 | December 2026 | 100% | 98 of 106 booked (92%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 35% | 70 | |
| 100% | 0% | 0% | 52 | |
| 100% | 0% | 0% | 1 | |
| 70% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Elegance Vega (MahaRERA P52100049473) is a residential project by Elegance Landmarks in Baner, Pune 411045. It was launched in February 2023. It has 74 units in 2 buildings: 63 homes (2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 6 months from the original June 2026. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 98% complete, final finishes 35% complete. MahaRERA records do not show it as ready to move in.
70 of its 74 units are booked (95%). Since the December 2025 update, 18 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 98% and the possession date has moved from June 2026 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.