Sai Darshan Phase II, Tathawade
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Sai Shraddha Developers. Tathawade, Pune 411033. View on Google Maps
- Launched
- 2 years 9 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 1 year (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 16 of 4833% booked
Project facts
| 2 BHK | 48 |
|---|---|
| Total units | 48 |
| Buildings | 2 |
| Land | 0.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 15 → 16 · structure 95% → 100% · final finishes 93% → 100% · possession date December 2025 → December 2026
Compared with 6 similar projects in PIN 411033
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 9 mths | 2 yrs 8 mths |
| Possession date extended | By 1 year | 3 of 6 |
| Possession date (MahaRERA) | December 2026 | November 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 33% | 56% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| VLD Heritage | March 2023 | December 2025 | 100% | 8 of 31 booked (26%) |
| Sentosa Pride Wing A | March 2023 | June 2026 | 100% | 85 of 91 booked (93%) |
| Yashwant Audumbar A Wing | April 2023 | March 2027 | 100% | 22 of 34 booked (65%) |
| Pooja Co-op. Hsg. Soc. Ltd. | April 2023 | June 2025 | 87% | 23 of 26 booked (88%) |
| Bhakti Rudved | June 2023 | June 2026 | 100% | 21 of 46 booked (46%) |
| Sai Aarav | December 2022 | July 2026 | 50% | 25 of 63 booked (40%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 16 | |
| 100% | 95% | 93% | 15 | |
| 100% | 75% | 0% | 2 | |
| 100% | 45% | 0% | 1 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Sai Darshan Phase II (MahaRERA P52100050010) is a residential project by Sai Shraddha Developers in Tathawade, Pune 411033. It was launched in March 2023. It has 48 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
16 of its 48 units are booked (33%). Since the December 2025 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 95% to 100% and the possession date has moved from December 2025 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.