Skip to main content
← Back

Sushila, Dhayari

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Parulekarkale Realty LLP. Dhayari, Pune 411041. View on Google Maps

Launched
2 years 1 month originally promised
Possession date (MahaRERA)
7 months ago. No further extension recordedExtended by 9 months (originally June 2025). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
17 of 2471% booked

Project facts

1 BHK1
2 BHK22
3 BHK1
Total units24
Buildings1
Land0.1 acres
Landowner share4
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 14 → 17 · final finishes 25% → 100%

Share on WhatsApp

Compared with 4 similar projects in PIN 411041

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411041
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 1 mth2 yrs 10 mths
Possession date extendedBy 9 months2 of 4
Possession date passedYes, due March 20262 ready to move; 0 also past their date
Concrete structure (RCC) complete100%95%
Share of units booked71%24%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 60%Dec 2024: Concrete structure (RCC) 60%Jun 2025: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%17
100%100%25%14
100%60%0%—
100%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Sushila (MahaRERA P52100050888) is a residential project by Parulekarkale Realty LLP in Dhayari, Pune 411041. It was launched in May 2023. It has 24 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2026, after an extension of 9 months from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

17 of its 24 units are booked (71%). Since the December 2025 update, 3 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050888.Check it on MahaRERA (P52100050888)All projects in Dhayari