Mangalam Melizma, Kiwale
by Ved Mangalam Associates. Kiwale, Pune 412101. View on Google Maps
- Launched
- 3 years 7 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 99%Mid-constructionAverage across 2 buildings
- Units booked
- 254 of 36470% booked
Project facts
| 2 BHK | 122 |
|---|---|
| 3 BHK | 230 |
| Other units (shops, offices or not given by type) | 12 |
| Total units | 364 |
| Buildings | 2 |
| Land | 2.1 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 252 → 254 · structure 100% → 99%
Compared with 6 similar projects in PIN 412101
Projects with 150–800 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 7 mths | 4 yrs 6 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | December 2026 | December 2027 |
| Concrete structure (RCC) complete | 99% | 67% |
| Share of units booked | 70% | 84% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Yashada Windsong | May 2023 | December 2026 | 100% | 404 of 413 booked (98%) |
| The Rising | April 2023 | July 2027 | 100% | 279 of 348 booked (80%) |
| Gini Vivante Phase 02 | April 2023 | December 2027 | 47% | 523 of 621 booked (84%) |
| ACE Atmosphere Phase I | July 2023 | September 2028 | 34% | 306 of 340 booked (90%) |
| Sparkle at Godrej Serene | January 2023 | December 2027 | 0% | Bookings not reported |
| Presidential Towers | September 2022 | June 2028 | 87% | 504 of 655 booked (77%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 99% | 0% | 254 | |
| 100% | 100% | 0% | 252 | |
| 100% | 68% | 0% | 238 | |
| 100% | 8% | 0% | 43 | |
| 0% | 0% | 0% | 43 |
"—" means MahaRERA shows no figure for that update.
About this project
Mangalam Melizma (MahaRERA P52100051095) is a residential project by Ved Mangalam Associates in Kiwale, Pune 412101. It was launched in May 2023. It has 364 units in 2 buildings: 352 homes (2 & 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 99% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
254 of its 364 units are booked (70%). Since the December 2025 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 100% to 99%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.