Nirman Cosmopolis, Tathawade

by Realcon Properties LLP. Tathawade, Pune 411033. View on Google Maps

Launched
7 years 6 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
93%Mid-constructionAverage across 5 buildings
Units booked
413 of 55475% booked
Price per sq ft (incl. balconies and terrace)
₹10,7002026 so far · 64 salesdown 1% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK76
3 BHK273
4 BHK5
Other units (shops, offices or not given by type)200
Total units554
Buildings5
Land5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 320 → 413 · structure 31% → 93% · final finishes 0% → 24%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,080 sq ft₹1.13 – 1.17 crore
1,210 – 1,230 sq ft₹1.29 – 1.35 crore
1,930 sq ft₹1.90 – 1.98 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,100 per sq ft141 sales
2025up 7% on 2024₹10,800 per sq ft92 sales
2026 so fardown 1% on 2025₹10,700 per sq ft64 sales

Rate vs other Tathawade projects, 2026: about 5% higher

Compared with 6 similar projects in PIN 411033

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)7 yrs 6 mths4 yrs 4 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)December 2030November 2027
Concrete structure (RCC) complete93%100%
Share of units booked75%70%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 4 months of the promised 7 years 6 months have passed
Concrete structure (RCC) 93% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 33%Jun 2024: Excavation 65%Dec 2024: Excavation 80%Jun 2025: Excavation 80%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 31%Jul 2026: Concrete structure (RCC) 93%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 24%Excavation 100%Concrete structure (RCC) 93%Final finishes 24%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%24%413
100%31%0%320
80%0%0%176
65%0%0%176
33%0%0%145

"—" means MahaRERA shows no figure for that update.

About this project

Nirman Cosmopolis (MahaRERA P52100051380) is a residential project by Realcon Properties LLP in Tathawade, Pune 411033. It was launched in June 2023. It has 554 units in 5 buildings: 354 homes (2, 3 & 4 BHK) and 200 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) 93% complete, final finishes 24% complete. MahaRERA records do not show it as ready to move in.

413 of its 554 units are booked (75%). Since the December 2025 update, 93 more units have been booked and the reported concrete structure (RCC) has gone from 31% to 93%. 80% of the 2026 (so far) sales we found here were at ₹10,700 per sq ft or less (down 1% on 2025), counting balconies and terrace in the size, based on 64 registered sales. Buyers here paid a rate about 5% higher than at other Tathawade projects in 2026. Most buyers paid ₹1.13–1.17 crore for flats of 1,080 sq ft, ₹1.29–1.35 crore for 1,210–1,230 sq ft and ₹1.90–1.98 crore for 1,930 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100051380.Check it on MahaRERA (P52100051380)All projects in Tathawade, Punawale, Jambhe