K Shire Phase 2, Punawale

by Unique Spaces LLP. Punawale, Pune 411033. View on Google Maps

Launched
4 years 7 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
317 of 39780% booked
Price per sq ft (incl. balconies and terrace)
₹9,2002026 so far · 74 salesup 2% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK6
3 BHK231
4 BHK160
Total units397
Buildings3
Land3.4 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 208 → 317 · structure 81% → 100% · final finishes 0% → 72%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,020 – 1,040 sq ft₹82 – 94 lakh
1,330 sq ft₹1.14 – 1.25 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹8,800 per sq ft142 sales
2025up 2% on 2024₹9,000 per sq ft95 sales
2026 so farup 2% on 2025₹9,200 per sq ft74 sales

Rate vs other Punawale projects, 2026: similar

Compared with 6 similar projects in PIN 411033

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 7 mths4 yrs 4 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)December 2027November 2027
Concrete structure (RCC) complete100%100%
Share of units booked80%70%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 5 months of the promised 4 years 7 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 67%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 22%Dec 2024: Concrete structure (RCC) 65%Jun 2025: Concrete structure (RCC) 65%Dec 2025: Concrete structure (RCC) 81%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 72%Excavation 100%Concrete structure (RCC) 100%Final finishes 72%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%72%317
100%81%0%208
100%65%0%208
100%22%0%148
67%0%0%44

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

K Shire Phase 2 (MahaRERA P52100050966) is a residential project by Unique Spaces LLP in Punawale, Pune 411033. It was launched in May 2023. It has 397 units in 3 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 72% complete. MahaRERA records do not show it as ready to move in.

317 of its 397 units are booked (80%). Since the December 2025 update, 109 more units have been booked and the reported concrete structure (RCC) has gone from 81% to 100%. 80% of the 2026 (so far) sales we found here were at ₹9,200 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size, based on 74 registered sales. Buyers here paid a rate similar to other Punawale projects in 2026. Most buyers paid ₹82–94 lakh for flats of 1,020–1,040 sq ft and ₹1.14–1.25 crore for 1,330 sq ft.

Unique's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA8
Completed without extending the possession date4
Completed after an extension, or lapsed0
Under construction4
Possession date extended by the builder0
Typical time from launch to 100% structure2 years 4 months
Complaints on MahaRERA, all Unique projects4 (3 of 8 projects)

See all Unique projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050966.Check it on MahaRERA (P52100050966)All projects in Tathawade, Punawale, Jambhe