Skip to main content
← Back

Avantika, Kothrud

by Ranjekar Realty LLP. Kothrud, Pune 411038. View on Google Maps

Launched
3 years 6 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
12 of 5223% booked

Project facts

1 BHK1
2 BHK27
3 BHK14
4 BHK10
Total units52
Buildings1
Land0.3 acres
Landowner share23
Rehab units1
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 6 → 12 · total units 51 → 52

Share on WhatsApp

Compared with 6 similar projects in PIN 411038

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 6 mths3 yrs
Possession date extendedNo3 of 6
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete0%100%
Share of units booked23%30%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 4 months of the promised 3 years 6 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 80%Dec 2024: Excavation 80%Jun 2025: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%0%0%12
80%0%0%6
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Avantika (MahaRERA P52100051675) is a residential project by Ranjekar Realty LLP in Kothrud, Pune 411038. It was launched in June 2023. It has 52 units in 1 building, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 80% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

12 of its 52 units are booked (23%). Since the December 2025 update, 6 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100051675.Check it on MahaRERA (P52100051675)All projects in Kothrud