Skip to main content
← Back

Lotus Yojangandha, Kothrud

by Lotus Yojangandha Developers. Kothrud, Pune 411038. View on Google Maps

Launched
3 years 2 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
26 of 11922% booked
Price per sq ft (incl. balconies and terrace)
₹15,0002026 so far · 12 salesup 14% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK1
2 BHK44
3 BHK45
4 BHK21
Other units (shops, offices or not given by type)8
Total units119
Buildings2
Land0.6 acres
Landowner share67
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 24 → 26 · structure 63% → 100%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹14,100 per sq ft11 sales
2025down 6% on 2024₹13,200 per sq ft10 sales
2026 so farup 14% on 2025₹15,000 per sq ft12 sales

Rate vs other Kothrud projects, 2026: about 10% lower

Compared with 6 similar projects in PIN 411038

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 2 mths4 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2026December 2027
Concrete structure (RCC) complete100%5%
Share of units booked22%23%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 3 years 2 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 18%Jun 2025: Concrete structure (RCC) 18%Dec 2025: Concrete structure (RCC) 63%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%26
100%63%0%24
100%18%0%81
100%0%0%7
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Lotus Yojangandha (MahaRERA P52100053370) is a residential project by Lotus Yojangandha Developers in Kothrud, Pune 411038. It was launched in October 2023. It has 119 units in 2 buildings: 111 homes (1 RK, 2 BHK, 3 BHK & 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

26 of its 119 units are booked (22%). Since the December 2025 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 63% to 100%. 80% of the 2026 (so far) sales we found here were at ₹15,000 per sq ft or less (up 14% on 2025), counting balconies and terrace in the size, based on 12 registered sales. Buyers here paid a rate about 10% lower than at other Kothrud projects in 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053370.Check it on MahaRERA (P52100053370)All projects in Kothrud