Skip to main content
← Back

Vasundhara, Kothrud

by Dake-Ranjekar JV. Kothrud, Pune 411038. View on Google Maps

Launched
3 years 10 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
83%Mid-construction
Units booked
68 of 10366% booked
Price per sq ft (incl. balconies and terrace)
₹15,3002026 so far · 14 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK42
3 BHK61
Total units103
Buildings1
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 71% → 83%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
870 – 970 sq ft₹1.21 – 1.38 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹15,300 per sq ft14 sales

Rate vs other Kothrud projects, 2026: about 5% lower

Compared with 5 similar projects in PIN 411038

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths3 yrs 6 mths
Possession date extendedNo2 of 5
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete83%100%
Share of units booked66%48%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 8 months of the promised 3 years 10 months have passed
Concrete structure (RCC) 83% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 71%Jul 2026: Concrete structure (RCC) 83%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 83%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%83%10%68
100%71%10%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Vasundhara (MahaRERA P52100049328) is a residential project by Dake-Ranjekar JV in Kothrud, Pune 411038. It was launched in February 2023. It has 103 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 83% complete, final finishes 10% complete. MahaRERA records do not show it as ready to move in.

68 of its 103 units are booked (66%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 71% to 83%. 80% of the 2026 (so far) sales we found here were at ₹15,300 per sq ft or less, counting balconies and terrace in the size, based on 14 registered sales. Buyers here paid a rate about 5% lower than at other Kothrud projects in 2026. Most buyers paid ₹1.21–1.38 crore for flats of 870–970 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100049328.Check it on MahaRERA (P52100049328)All projects in Kothrud