18 Magnitude, Punawale
by GD Square Spaces. Punawale, Pune 411033. View on Google Maps
- Launched
- 5 years 3 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 92%Mid-constructionAverage across 5 buildings
- Units booked
- 299 of 50459% booked
Project facts
| 1 RK | 3 |
|---|---|
| 1 BHK | 12 |
| 2 BHK | 366 |
| 3 BHK | 80 |
| Other units (shops, offices or not given by type) | 43 |
| Total units | 504 |
| Buildings | 5 |
| Land | 2.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 75% → 92%
Compared with 6 similar projects in PIN 411033
Projects with 200–1,000 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 3 mths | 4 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2028 | December 2027 |
| Concrete structure (RCC) complete | 92% | 80% |
| Share of units booked | 59% | 72% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mahindra Happinest Tathawade Phase 3 | September 2023 | December 2027 | 0% | 284 of 496 booked (57%) |
| Rohan Harita Phase 1 | October 2023 | December 2027 | 96% | 460 of 499 booked (92%) |
| Grand Exotica | August 2023 | December 2026 | 0% | 221 of 483 booked (46%) |
| 41 Zillenia | July 2023 | September 2027 | 100% | 474 of 544 booked (87%) |
| Millennium Falcon | December 2023 | December 2028 | 86% | 442 of 478 booked (92%) |
| Nexus Skydale | February 2024 | December 2027 | 75% | 309 of 578 booked (53%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 92% | 0% | 299 | |
| 100% | 75% | 0% | 299 | |
| 80% | 57% | 0% | 144 | |
| 80% | 15% | 0% | 144 | |
| 72% | 0% | 0% | 9 |
"—" means MahaRERA shows no figure for that update.
About this project
18 Magnitude (MahaRERA P52100052534) is a residential project by GD Square Spaces in Punawale, Pune 411033. It was launched in September 2023. It has 504 units in 5 buildings: 461 homes (1 RK, 1 BHK, 2 BHK & 3 BHK) and 43 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) 92% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
299 of its 504 units are booked (59%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 75% to 92%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.