Skip to main content
← Back

Mahindra Happinest Tathawade Phase 3

by Mahindra Lifespace Developers limited. Tathawade, Pune 411033. View on Google Maps

Launched
4 years 3 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
284 of 49657% booked
Price per sq ft (incl. balconies and terrace)
₹10,0002025 · 193 salesup 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK430
Other units (shops, offices or not given by type)66
Total units496
Buildings2
Land2.3 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
620 sq ft₹61 – 62 lakh
700 sq ft₹69 – 72 lakh

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹9,800 per sq ft212 sales
2025up 2% on 2024₹10,000 per sq ft193 sales

Rate vs other Tathawade projects, 2025: about 10% higher

Compared with 6 similar projects in PIN 411033

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 3 mths4 yrs 3 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2027December 2027
Concrete structure (RCC) complete0%94%
Share of units booked57%90%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 1 month of the promised 4 years 3 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%284
100%0%0%112
100%0%0%22

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Mahindra Happinest Tathawade Phase 3 (MahaRERA P52100052559) is a residential project by Mahindra Lifespace Developers limited in Tathawade, Pune 411033. It was launched in September 2023. It has 496 units in 2 buildings: 430 homes (2 BHK) and 66 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

284 of its 496 units are booked (57%). 80% of the 2025 sales we found here were at ₹10,000 per sq ft or less (up 2% on 2024), counting balconies and terrace in the size, based on 193 registered sales. Buyers here paid a rate about 10% higher than at other Tathawade projects in 2025. Most buyers paid ₹61–62 lakh for flats of 620 sq ft and ₹69–72 lakh for 700 sq ft.

Mahindra's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA27
Completed without extending the possession date13
Completed after an extension, or lapsed0
Under construction14
Possession date extended by the builder2
Complaints on MahaRERA, all Mahindra projects11 (9 of 27 projects)

See all Mahindra projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052559.Check it on MahaRERA (P52100052559)All projects in Tathawade, Punawale, Jambhe