Skip to main content
← Back

Pristine Allure Part 3, Kharadi

by Mahalaxmi Shelters. Kharadi, Pune 411014. View on Google Maps

Launched
4 years 3 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
51%Mid-constructionAverage across 2 buildings
Units booked
82 of 13660% booked

Project facts

2 BHK16
3 BHK62
Other units (shops, offices or not given by type)58
Total units136
Buildings2
Land2 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 31% → 51%

Share on WhatsApp

Compared with 5 similar projects in PIN 411014

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 3 mths3 yrs 8 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)December 2027April 2027
Concrete structure (RCC) complete51%95%
Share of units booked60%82%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 1 month of the promised 4 years 3 months have passed
Concrete structure (RCC) 51% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 31%Jul 2026: Concrete structure (RCC) 51%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 51%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%51%0%82
95%31%0%82
100%0%0%65
0%0%0%59
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Pristine Allure Part 3 (MahaRERA P52100052693) is a residential project by Mahalaxmi Shelters in Kharadi, Pune 411014. It was launched in September 2023. It has 136 units in 2 buildings: 78 homes (2 & 3 BHK) and 58 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 51% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

82 of its 136 units are booked (60%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 31% to 51%.

Pristine's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA25
Completed without extending the possession date13
Completed after an extension, or lapsed1
Under construction11
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 7 months
Complaints on MahaRERA, all Pristine projects18 (6 of 25 projects)

See all Pristine projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052693.Check it on MahaRERA (P52100052693)All projects in Kharadi, Vadgaon Sheri, Viman Nagar