VJ Central Avenue, Kharadi

by Vilas Javdekar Eco Homes. Kharadi, Pune 411014. View on Google Maps

Launched
3 years 8 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
95%Mid-constructionAverage across 2 buildings
Units booked
672 of 77886% booked
Price per sq ft (incl. balconies and terrace)
₹15,300studios · 2025 · 11 salesdown 13% on 202480% of the 2025 studio sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK109
Other units (shops, offices or not given by type)669
Total units778
Buildings2
Land1.3 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 678 → 672 · structure 90% → 95%

Share on WhatsApp

What buyers paid here

Studios (under 450 sq ft)

₹15,300 per sq ft · studios · 2025 · 11 sales

80% of the 2025 studio sales we found were at this rate or less

2024₹17,500 per sq ft15 sales
2025down 13% on 2024₹15,300 per sq ft11 sales

Sizes 370 – 380 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Compared with 6 similar projects in PIN 411014

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 8 mths4 yrs 1 mth
Possession date extendedNo2 of 6
Possession date (MahaRERA)December 2026December 2027
Concrete structure (RCC) complete95%64%
Share of units booked86%73%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 6 months of the promised 3 years 8 months have passed
Concrete structure (RCC) 95% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 85%Jun 2024: Excavation 85%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 35%Dec 2024: Concrete structure (RCC) 70%Jun 2025: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 95%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%672
100%90%0%678
100%70%0%226
85%35%0%714
85%0%0%570

"—" means MahaRERA shows no figure for that update.

About this project

VJ Central Avenue (MahaRERA P52100050364) is a residential project by Vilas Javdekar Eco Homes in Kharadi, Pune 411014. It was launched in April 2023. It has 778 units in 2 buildings: 109 homes (1 BHK) and 669 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 95% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

672 of its 778 units are booked (86%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 90% to 95%. Its studios (under 450 sq ft) sold at ₹15,300 per sq ft or less in 2025 (11 sales); studios are priced separately from flats.

Vilas Javdekar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA45
Completed without extending the possession date25
Completed after an extension, or lapsed1
Under construction19
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 10 months
Complaints on MahaRERA, all Vilas Javdekar projects27 (19 of 45 projects)

See all Vilas Javdekar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050364.Check it on MahaRERA (P52100050364)All projects in Kharadi, Vadgaon Sheri, Viman Nagar