Envogue 1, Mundhwa

by Unique Spaces Landmarks LLP. Mundhwa, Pune 411036. View on Google Maps

Launched
5 years 2 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
97%Mid-constructionAverage across 3 buildings
Units booked
87 of 8998% booked
Price per sq ft (incl. balconies and terrace)
₹12,5002026 so far · 50 salesup 8% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK6
2 BHK32
3 BHK6
4 BHK45
Total units89
Name as registered on MahaRERAENVOGUE1
Buildings3
Land1.7 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 83 → 87 · structure 58% → 97% · final finishes 0% → 77% · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,410 – 1,450 sq ft₹1.51 – 1.88 crore
1,940 – 1,950 sq ft₹1.97 – 2.40 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,900 per sq ft32 sales
2025up 6% on 2024₹11,600 per sq ft47 sales
2026 so farup 8% on 2025₹12,500 per sq ft50 sales

Rate vs other Mundhwa projects, 2026: about 10% higher

Compared with 6 similar projects in PIN 411036

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411036
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2028December 2027
Concrete structure (RCC) complete97%22%
Share of units booked98%66%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 5 years 2 months have passed
Concrete structure (RCC) 97% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 50%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 3%Dec 2024: Concrete structure (RCC) 22%Jun 2025: Concrete structure (RCC) 22%Dec 2025: Concrete structure (RCC) 58%Jul 2026: Concrete structure (RCC) 97%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 77%Excavation 100%Concrete structure (RCC) 97%Final finishes 77%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%77%87
100%58%0%83
100%22%0%75
50%3%0%25
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Envogue 1 (MahaRERA P52100053239) is a residential project by Unique Spaces Landmarks LLP in Mundhwa, Pune 411036. It was launched in October 2023. It has 89 units in 3 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 97% complete, final finishes 77% complete. MahaRERA records do not show it as ready to move in.

87 of its 89 units are booked (98%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 58% to 97%. 80% of the 2026 (so far) sales we found here were at ₹12,500 per sq ft or less (up 8% on 2025), counting balconies and terrace in the size, based on 50 registered sales. Buyers here paid a rate about 10% higher than at other Mundhwa projects in 2026. Most buyers paid ₹1.51–1.88 crore for flats of 1,410–1,450 sq ft and ₹1.97–2.40 crore for 1,940–1,950 sq ft.

Unique's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA8
Completed without extending the possession date4
Completed after an extension, or lapsed0
Under construction4
Possession date extended by the builder0
Typical time from launch to 100% structure2 years 4 months
Complaints on MahaRERA, all Unique projects4 (3 of 8 projects)

See all Unique projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053239.Check it on MahaRERA (P52100053239)All projects in Mundhwa, Keshavnagar