Hillview Residency Building I, Kothrud
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Kumar Beharay Properties LLP. Kothrud, Pune 411038. View on Google Maps
- Launched
- 3 years 1 month promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 65 of 7686% booked
Project facts
| 2 BHK | 41 |
|---|---|
| 3 BHK | 35 |
| Total units | 76 |
| Buildings | 1 |
| Land | 1 acre |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 64 → 65 · final finishes 0% → 100%
Compared with 6 similar projects in PIN 411038
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 1 mth | 4 yrs 2 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2026 | January 2028 |
| Concrete structure (RCC) complete | 100% | 5% |
| Share of units booked | 86% | 26% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Anant | November 2023 | December 2026 | 100% | 21 of 60 booked (35%) |
| Mokate Kalanidhi | November 2023 | December 2028 | 10% | 3 of 121 booked (2%) |
| Dashabhuja | October 2023 | December 2027 | 0% | 24 of 105 booked (23%) |
| Shri Keshavlaxmi | December 2023 | March 2028 | 0% | 22 of 52 booked (42%) |
| Lotus Yojangandha | October 2023 | December 2026 | 100% | 26 of 119 booked (22%) |
| Solitaire Kothrud A Building | May 2024 | June 2029 | 0% | 41 of 139 booked (29%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 65 | |
| 100% | 100% | 0% | 64 | |
| 100% | 100% | 0% | 57 | |
| 100% | 81% | 0% | — | |
| 100% | 94% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Hillview Residency Building I (MahaRERA P52100053658) is a residential project by Kumar Beharay Properties LLP in Kothrud, Pune 411038. It was launched in November 2023. It has 76 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
65 of its 76 units are booked (86%). Since the December 2025 update, 1 more unit has been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.