Skip to main content
← Back

Solitaire Kothrud A Building

by Built to Live Realty Development NO 1 LLP. Kothrud, Pune 411038. View on Google Maps

Launched
5 years 1 month promised
Possession date (MahaRERA)
2 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
41 of 13929% booked
Price per sq ft (incl. balconies and terrace)
₹18,1002026 so far · 13 salesup 5% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK1
3 BHK43
4 BHK88
Other units (shops, offices or not given by type)7
Total units139
Buildings1
Land1.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 34 → 41

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,310 – 1,530 sq ft₹2.22 – 2.27 crore

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹17,200 per sq ft20 sales
2026 so farup 5% on 2025₹18,100 per sq ft13 sales

Rate vs other Kothrud projects, 2026: about 10% higher

Compared with 5 similar projects in PIN 411038

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 1 mth3 yrs 10 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)June 2029March 2028
Concrete structure (RCC) complete0%13%
Share of units booked29%26%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 5 months of the promised 5 years 1 month have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%41
100%0%0%34
0%0%0%3
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Solitaire Kothrud A Building (MahaRERA P52100056306) is a residential project by Built to Live Realty Development NO 1 LLP in Kothrud, Pune 411038. It was launched in May 2024. It has 139 units in 1 building: 132 homes (2, 3 & 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

41 of its 139 units are booked (29%). Since the December 2025 update, 7 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹18,100 per sq ft or less (up 5% on 2025), counting balconies and terrace in the size, based on 13 registered sales. Buyers here paid a rate about 10% higher than at other Kothrud projects in 2026. Most buyers paid ₹2.22–2.27 crore for flats of 1,310–1,530 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100056306.Check it on MahaRERA (P52100056306)All projects in Kothrud