Skip to main content
← Back

Spandan, Vadgaon Sheri

by Evolve Infra. Vadgaon Sheri, Pune 411014. View on Google Maps

Launched
2 years 10 months promised
Possession date (MahaRERA)
This monthPossession date unchanged since launch
Concrete structure (RCC)
95%Mid-construction
Units booked
9 of 2438% booked

Project facts

2 BHK24
Total units24
Buildings1
Land0.2 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 5 → 9 · structure 60% → 95% · final finishes 5% → 25%

Share on WhatsApp

Compared with 6 similar projects in PIN 411014

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths3 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)October 2026December 2027
Concrete structure (RCC) complete95%75%
Share of units booked38%64%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 2 years 10 months have passed
Concrete structure (RCC) 95% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 95%Dec 2024: Excavation 90%Jun 2025: Excavation 90%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 15%Jun 2025: Concrete structure (RCC) 15%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 95%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 5%Jul 2026: Final finishes 25%Excavation 95%Concrete structure (RCC) 95%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%95%25%9
95%60%5%5
90%15%0%—
95%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Spandan (MahaRERA P52100053983) is a residential project by Evolve Infra in Vadgaon Sheri, Pune 411014. It was launched in December 2023. It has 24 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2026, unchanged since launch. Construction: excavation 95% complete, structure (RCC) 95% complete, final finishes 25% complete. MahaRERA records do not show it as ready to move in.

9 of its 24 units are booked (38%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 95%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053983.Check it on MahaRERA (P52100053983)All projects in Kharadi, Vadgaon Sheri, Viman Nagar