Kumar Palaash A2, Vadgaon Sheri
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Kumar & Potnis Associates. Vadgaon Sheri, Pune 411014. View on Google Maps
- Launched
- 4 years 11 months promised
- Possession date (MahaRERA)
- 2 years awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- All booked35 units booked
Project facts
| 2 BHK | 35 |
|---|---|
| Total units | 35 |
| Buildings | 1 |
| Land | 0.1 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: final finishes 37% → 100%
Compared with 4 similar projects in PIN 411014
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 11 mths | 2 yrs 9 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | October 2028 | December 2026 |
| Concrete structure (RCC) complete | 100% | 82% |
| Share of units booked | 100% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aleria - Block B | October 2023 | June 2026 | 100% | All 27 units booked |
| Spandan | December 2023 | October 2026 | 95% | 9 of 24 booked (38%) |
| Highlife Survey NO 56/3/37/1P , 56/3/26/3 at Wadgaonsheri | May 2024 | December 2026 | 45% | 5 of 34 booked (15%) |
| VJ IndiLife Kharadi | May 2024 | December 2028 | 70% | 813 of 835 booked (97%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 35 | |
| 100% | 100% | 37% | 35 | |
| 100% | 100% | 56% | 31 | |
| 100% | 56% | 56% | 12 | |
| 100% | 22% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Kumar Palaash A2 (MahaRERA P52100053742) is a residential project by Kumar & Potnis Associates in Vadgaon Sheri, Pune 411014. It was launched in November 2023. It has 35 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
All 35 units are booked.
Kumar's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 82 |
|---|---|
| Completed without extending the possession date | 42 |
| Completed after an extension, or lapsed | 5 |
| Under construction | 35 |
| Possession date extended by the builder | 5 |
| Typical time from launch to 100% structure | 2 years 6 months |
| Complaints on MahaRERA, all Kumar projects | 71 (8 of 82 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.