Devki Co-operative Housing Society Limited, Kothrud
Finishing stageLapsed
Final finishes 100% · completion not yet filed on MahaRERA
by Shreesha Landmark. Kothrud, Pune 411029. View on Google Maps
- Launched
- 2 years 5 months promised
- Possession date (MahaRERA)
- 4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 12 of 2255% booked
- Price per sq ft (incl. balconies and terrace)
- ₹14,4002025 · 12 sales80% of the 2025 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 BHK | 2 |
|---|---|
| 2 BHK | 7 |
| 3 BHK | 13 |
| Total units | 22 |
| Buildings | 1 |
| Land | 0.1 acres |
| Landowner share | 10 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 4 → 12 · final finishes 0% → 100%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2025 | ₹14,400 per sq ft | 12 sales |
|---|
Rate vs other Kothrud projects, 2025: about 15% lower
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 12 | |
| 100% | 100% | 0% | 4 | |
| 100% | 0% | 0% | 10 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Devki Co-operative Housing Society Limited (MahaRERA P52100054183) is a residential project by Shreesha Landmark in Kothrud, Pune 411029. It was launched in January 2024. It has 22 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
12 of its 22 units are booked (55%). Since the December 2025 update, 8 more units have been booked. 80% of the 2025 sales we found here were at ₹14,400 per sq ft or less, counting balconies and terrace in the size, based on 12 registered sales. Buyers here paid a rate about 15% lower than at other Kothrud projects in 2025.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.