Skip to main content
← Back

Dolphin Palms Wings C, D and E, Ravet

by M/S Dolphin Realty. Ravet, Pune 412101. View on Google Maps

Launched
3 years promised
Possession date (MahaRERA)
5 months awayPossession date unchanged since launch
Concrete structure (RCC)
79%Mid-constructionAverage across 3 buildings
Units booked
140 of 17879% booked
Price per sq ft (incl. balconies and terrace)
₹9,4002026 so far · 11 salesup 13% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK7
2 BHK132
3 BHK39
Total units178
Buildings3
Land0.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 136 → 140 · structure 26% → 79%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
560 – 610 sq ft₹32 – 44 lakh
760 – 770 sq ft₹52 – 64 lakh
850 – 890 sq ft₹67 – 73 lakh

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹8,100 per sq ft25 sales
2025up 2% on 2024₹8,300 per sq ft115 sales
2026 so farup 13% on 2025₹9,400 per sq ft11 sales

Rate vs other Ravet projects, 2026: about 5% higher

Compared with 6 similar projects in PIN 412101

Projects with 80–400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)March 2027June 2028
Concrete structure (RCC) complete79%98%
Share of units booked79%79%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 7 months of the promised 3 years have passed
Concrete structure (RCC) 79% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 26%Jul 2026: Concrete structure (RCC) 79%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 79%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%140
100%26%0%136
100%0%0%23
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Dolphin Palms Wings C, D and E (MahaRERA P52100055197) is a residential project by M/S Dolphin Realty in Ravet, Pune 412101. It was launched in March 2024. It has 178 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 79% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

140 of its 178 units are booked (79%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 26% to 79%. 80% of the 2026 (so far) sales we found here were at ₹9,400 per sq ft or less (up 13% on 2025), counting balconies and terrace in the size, based on 11 registered sales. Buyers here paid a rate about 5% higher than at other Ravet projects in 2026. Most buyers paid ₹32–44 lakh for flats of 560–610 sq ft, ₹52–64 lakh for 760–770 sq ft and ₹67–73 lakh for 850–890 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055197.Check it on MahaRERA (P52100055197)All projects in Kiwale, Ravet