Isle of Life - Building B and C, Marunji
by R R Ventures. Marunji, Pune 411033. View on Google Maps
- Launched
- 1 year 6 months originally promised
- Possession date (MahaRERA)
- 2 months agoExtended by 1 year (originally August 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 326 of 33099% booked
- Price per sq ft (incl. balconies and terrace)
- ₹12,400studios · 2026 so far · 15 salesabout the same as 202580% of the 2026 studio sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 RK | 330 |
|---|---|
| Total units | 330 |
| Buildings | 2 |
| Land | 1.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 249 → 326 · final finishes 0% → 73% · total units 274 → 330
What buyers paid here
Studios (under 450 sq ft)
₹12,400 per sq ft · studios · 2026 so far · 15 sales
80% of the 2026 studio sales we found were at this rate or less
| 2024 | ₹10,600 per sq ft | 153 sales |
|---|---|---|
| 2025up 17% on 2024 | ₹12,400 per sq ft | 145 sales |
| 2026 so farabout the same as 2025 | ₹12,400 per sq ft | 15 sales |
Sizes 190 – 210 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 73% | 326 | |
| 100% | 100% | 0% | 249 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Isle of Life - Building B and C (MahaRERA P52100055011) is a residential project by R R Ventures in Marunji, Pune 411033. It was launched in February 2024. It has 330 units in 2 buildings, with 1 RK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is August 2026, extended by 1 year from the original August 2025. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 73% complete. MahaRERA records do not show it as ready to move in.
326 of its 330 units are booked (99%). Since the December 2025 update, 77 more units have been booked. Its studios (under 450 sq ft) sold at ₹12,400 per sq ft or less in 2026 (15 sales); studios are priced separately from flats.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.