Evolvus Phase-II, Kharadi
by Townshine Realties Private Limited. Kharadi, Pune 411014. View on Google Maps
- Launched
- 4 years 7 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 3 buildings
- Units booked
- Bookings not reported
Project facts
| 2 BHK | 158 |
|---|---|
| 3 BHK | 128 |
| Other units (shops, offices or not given by type) | 32 |
| Total units | 318 |
| Buildings | 3 |
| Land | 2.3 acres |
| Landowner share | 32 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411014
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 7 mths | 4 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2028 | January 2029 |
| Concrete structure (RCC) complete | 0% | 27% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nyati Evoque | May 2024 | December 2027 | 27% | 41 of 217 booked (19%) |
| Pristine KYRA | April 2024 | March 2029 | 69% | 129 of 292 booked (44%) |
| Sun Emerald | March 2024 | December 2029 | 45% | 49 of 150 booked (33%) |
| Prasun Adara | July 2024 | May 2028 | 15% | 47 of 154 booked (31%) |
| Palladio Kharadi Central Phase 2 | October 2024 | December 2028 | 27% | 331 of 377 booked (88%) |
| Neco Park Central | October 2024 | June 2030 | 12% | 107 of 201 booked (53%) |
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Evolvus Phase-II (MahaRERA P52100056143) is a residential project by Townshine Realties Private Limited in Kharadi, Pune 411014. It was launched in May 2024. It has 318 units in 3 buildings: 286 homes (2 & 3 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.