Nyati Evoque, Vadgaon Sheri

by Nyati Builders Private Limited. Vadgaon Sheri, Pune 411014. View on Google Maps

Launched
3 years 7 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
27%Mid-constructionAverage across 3 buildings
Units booked
41 of 21719% booked
Price per sq ft (incl. balconies and terrace)
₹17,6002026 so far · 18 salesdown 1% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

3 BHK107
4 BHK89
Other units (shops, offices or not given by type)21
Total units217
Buildings3
Land1.8 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 30 → 41 · structure 15% → 27% · final finishes 0% → 1% · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,780 – 2,030 sq ft₹2.98 – 3.30 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹17,700 per sq ft19 sales
2026 so fardown 1% on 2025₹17,600 per sq ft18 sales

Compared with 6 similar projects in PIN 411014

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 7 mths4 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2027January 2029
Concrete structure (RCC) complete27%21%
Share of units booked19%44%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 5 months of the promised 3 years 7 months have passed
Concrete structure (RCC) 27% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 90%Dec 2024: Excavation 90%Jun 2025: Excavation 90%Dec 2025: Excavation 63%Jul 2026: Excavation 80%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 3%Jun 2025: Concrete structure (RCC) 3%Dec 2025: Concrete structure (RCC) 15%Jul 2026: Concrete structure (RCC) 27%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 1%Excavation 80%Concrete structure (RCC) 27%Final finishes 1%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%27%1%41
63%15%0%30
90%3%0%23
90%0%0%6

"—" means MahaRERA shows no figure for that update.

About this project

Nyati Evoque (MahaRERA P52100056152) is a residential project by Nyati Builders Private Limited in Vadgaon Sheri, Pune 411014. It was launched in May 2024. It has 217 units in 3 buildings: 196 homes (3 & 4 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation 80% complete, structure (RCC) 27% complete, final finishes 1% complete. MahaRERA records do not show it as ready to move in.

41 of its 217 units are booked (19%). Since the December 2025 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 15% to 27%. 80% of the 2026 (so far) sales we found here were at ₹17,600 per sq ft or less (down 1% on 2025), counting balconies and terrace in the size, based on 18 registered sales. Most buyers paid ₹2.98–3.30 crore for flats of 1,780–2,030 sq ft.

Nyati's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA48
Completed without extending the possession date24
Completed after an extension, or lapsed12
Under construction12
Possession date extended by the builder6
Typical time from launch to 100% structure2 years 1 month
Complaints on MahaRERA, all Nyati projects32 (14 of 48 projects)

See all Nyati projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100056152.Check it on MahaRERA (P52100056152)All projects in Kharadi, Vadgaon Sheri, Viman Nagar