33 Central Avenue, Tathawade

by Eisha Properties Unit 5. Tathawade, Pune 411033. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2028 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
0%Early stage0 of 2 phases with structure completeWeighted across 2 phases
Units booked
176 of 24771% booked · 1 phase not reported
Price per sq ft
₹10,1002026 salesup 5% on 2025See what buyers paid

Project facts

2 BHK326
3 BHK94
Total units420
Buildings2
Land5.3 acres
Phases2
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 750 – 770 sq ft₹74 – 79 lakh2026 sales
3 BHKabout 1,090 sq ft₹1.07 – 1.11 crore2026 sales

Price per sq ft, year by year

2024₹9,300 per sq ft
2025up 3% on 2024₹9,600 per sq ft
2026up 5% on 2025₹10,100 per sq ft

Registered sales across all 2 phases.

Compared with the typical Tathawade rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
33 Central Avenue Wing F-3
Early stage
P521000563992470%71%
33 Central Avenue Wing F-1
Early stage
PR12610125021721730%Not reported
Show updates by phase

33 Central Avenue Wing F-3 (P52100056399)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%176
0%0%0%31
0%0%0%—

"—" means MahaRERA shows no figure for that update.

33 Central Avenue Wing F-1 (PR1261012502172)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411033

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 3 mths4 yrs 5 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028 – Dec 2029September 2028
Concrete structure (RCC)0%8%
Units booked71%58%
MahaRERA complaints (filed by or against the builder)40

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

33 Central Avenue is a project by Eisha Properties Unit 5 in Tathawade, Pune 411033, registered with MahaRERA as 2 phases (P52100056399, PR1261012502172). The first phase was launched in May 2024. Together the phases have 420 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2028 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

176 of the 247 units reported for sale are booked (71%); 1 phase has not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹10,100 per sq ft or less (up 5% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Tathawade rate in 2026. Most buyers paid ₹74–79 lakh for 2 BHK flats of about 750–770 sq ft (2026 sales); ₹1.07–1.11 crore for 3 BHK flats of about 1,090 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100056399 and PR1261012502172.Open MahaRERA and search P52100056399All projects in Tathawade, Punawale, Jambhe