Sara City Plot E 1, Kharabwadi
by Jagrutsara Structures LLP. Kharabwadi, Pune 410501. View on Google Maps
- Launched
- 5 years 6 months promised
- Possession date (MahaRERA)
- 3 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 60%Mid-constructionAverage across 3 buildings
- Units booked
- 31 of 6448% booked
Project facts
| 1 BHK | 48 |
|---|---|
| Other units (shops, offices or not given by type) | 16 |
| Total units | 64 |
| Buildings | 3 |
| Land | 33 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 5 similar projects in PIN 410501
Projects with 20–100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 6 mths | 3 yrs |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | December 2029 | September 2027 |
| Concrete structure (RCC) complete | 60% | 93% |
| Share of units booked | 48% | 29% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Siddhivinayak Dream Homes C,D Wing | March 2024 | April 2026 | 75% | 17 of 84 booked (20%) |
| Dwarkadhish Park Building D | January 2024 | December 2028 | 100% | Bookings not reported |
| Sarangi Paradise | January 2024 | June 2027 | 93% | 39 of 84 booked (46%) |
| Swami Samarth Buildcon - Kalpavruksh Heights | December 2024 | December 2027 | 90% | 21 of 56 booked (38%) |
| Vallabh Heights | November 2023 | September 2026 | 100% | 1 of 27 booked (4%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 0% | 31 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Sara City Plot E 1 (MahaRERA P52100056494) is a residential project by Jagrutsara Structures LLP in Kharabwadi, Pune 410501. It was launched in June 2024. It has 64 units in 3 buildings: 48 homes (1 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 60% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
31 of its 64 units are booked (48%).
Sara's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 17 |
|---|---|
| Completed without extending the possession date | 1 |
| Completed after an extension, or lapsed | 5 |
| Under construction | 11 |
| Possession date extended by the builder | 2 |
| Typical time from launch to 100% structure | 1 year 10 months |
| Complaints on MahaRERA, all Sara projects | 0 (0 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.