Skip to main content
← Back

Sara City Tower C2, Kharabwadi

by Jagrutsara Structures LLP. Kharabwadi, Pune 410501. View on Google Maps

Launched
5 years 9 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
88 of 36124% booked

Project facts

1 BHK361
Total units361
Buildings1
Land33 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 3 similar projects in PIN 410501

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 410501
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 9 mths5 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2030December 2030
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 7 months of the promised 5 years 9 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%88
50%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Sara City Tower C2 (MahaRERA P52100079907) is a residential project by Jagrutsara Structures LLP in Kharabwadi, Pune 410501. It was launched in March 2025. It has 361 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

88 of its 361 units are booked (24%).

Sara's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA17
Completed without extending the possession date1
Completed after an extension, or lapsed5
Under construction11
Possession date extended by the builder2
Typical time from launch to 100% structure1 year 10 months
Complaints on MahaRERA, all Sara projects0 (0 of 17 projects)

See all Sara projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079907.Check it on MahaRERA (P52100079907)All projects in Chakan