Chandrabhaga, Erandwane
by Kotibhaskar Infrastructures &Developers Pvt. Ltd.. Erandwane, Pune 411004. View on Google Maps
- Launched
- 3 years originally promised
- Possession date (MahaRERA)
- 1 year 4 months awayExtended by 4 months (originally October 2027). Why possession dates change
- Concrete structure (RCC)
- 15%Mid-construction
- Units booked
- 16 of 5430% booked
Project facts
| 2 BHK | 28 |
|---|---|
| 3 BHK | 24 |
| 4 BHK | 2 |
| Total units | 54 |
| Buildings | 1 |
| Land | 0.3 acres |
| Rehab units | 23 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 15 → 16 · structure 0% → 15%
Compared with 5 similar projects in PIN 411004
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs | 3 yrs 4 mths |
| Possession date extended | By 4 months | 0 of 5 |
| Possession date (MahaRERA) | February 2028 | September 2027 |
| Concrete structure (RCC) complete | 15% | 60% |
| Share of units booked | 30% | 21% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Yashodhan Co-operative Housing Society | October 2024 | March 2028 | 60% | 8 of 56 booked (14%) |
| VB Sapphire | November 2024 | September 2027 | 50% | 2 of 37 booked (5%) |
| Kuldeep | July 2024 | June 2028 | 100% | 17 of 43 booked (40%) |
| Erandwane Business Zone | June 2024 | March 2027 | 100% | 19 of 91 booked (21%) |
| Venkatesh Erandwane Central Building A2 Phase 3 | February 2024 | June 2027 | 60% | 57 of 104 booked (55%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 15% | 0% | 16 | |
| 80% | 0% | 0% | 15 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Chandrabhaga (MahaRERA P52100077614) is a residential project by Kotibhaskar Infrastructures &Developers Pvt. Ltd. in Erandwane, Pune 411004. It was launched in October 2024. It has 54 units in 1 building, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is February 2028, extended by 4 months from the original October 2027. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
16 of its 54 units are booked (30%). Since the December 2025 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 0% to 15%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.