Triton Residency, Vadgaon Sheri
by M/S Sankalp Vastu LLP. Vadgaon Sheri, Pune 411014. View on Google Maps
- Launched
- 5 years 1 month promised
- Possession date (MahaRERA)
- 3 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 2 buildings
- Units booked
- 32 of 5360% booked
Project facts
| 2 BHK | 22 |
|---|---|
| 3 BHK | 31 |
| Total units | 53 |
| Buildings | 2 |
| Land | 0.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 23 → 32
Compared with 5 similar projects in PIN 411014
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 1 mth | 4 yrs 9 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | December 2029 | December 2029 |
| Concrete structure (RCC) complete | 0% | 17% |
| Share of units booked | 60% | 27% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Raichandani Aura | January 2025 | August 2028 | 0% | 26 of 90 booked (29%) |
| Anandi | February 2025 | December 2029 | 70% | Bookings not reported |
| Uday Heights | August 2024 | June 2026 | 100% | 71 of 80 booked (89%) |
| Palm Drive | February 2025 | December 2029 | 0% | 26 of 106 booked (25%) |
| Mangal Vastu | March 2025 | December 2029 | 17% | 18 of 108 booked (17%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 30% | 0% | 0% | 32 | |
| 30% | 0% | 0% | 23 | |
| 30% | 0% | 0% | 14 |
"—" means MahaRERA shows no figure for that update.
About this project
Triton Residency (MahaRERA P52100077881) is a residential project by M/S Sankalp Vastu LLP in Vadgaon Sheri, Pune 411014. It was launched in November 2024. It has 53 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation 30% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
32 of its 53 units are booked (60%). Since the December 2025 update, 9 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.