Palm Drive, Kharadi

by Ram India Landholding. Kharadi, Pune 411014. View on Google Maps

Launched
4 years 10 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
26 of 10625% booked
Price per sq ft (incl. balconies and terrace)
₹10,4002026 so far · 18 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK88
3 BHK18
Total units106
Buildings2
Land1.6 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
790 – 850 sq ft₹76 – 83 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹10,400 per sq ft18 sales

Rate vs other Kharadi projects, 2026: about 15% lower

Compared with 6 similar projects in PIN 411014

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 10 mths4 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)December 2029December 2029
Concrete structure (RCC) complete0%14%
Share of units booked25%48%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 8 months of the promised 4 years 10 months have passed
Concrete structure (RCC) 0% complete

Work not started as of Jul 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%26
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Palm Drive (MahaRERA P52100079176) is a residential project by Ram India Landholding in Kharadi, Pune 411014. It was launched in February 2025. It has 106 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

26 of its 106 units are booked (25%). 80% of the 2026 (so far) sales we found here were at ₹10,400 per sq ft or less, counting balconies and terrace in the size, based on 18 registered sales. Buyers here paid a rate about 15% lower than at other Kharadi projects in 2026. Most buyers paid ₹76–83 lakh for flats of 790–850 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079176.Check it on MahaRERA (P52100079176)All projects in Kharadi, Vadgaon Sheri, Viman Nagar