Majestique Towers East Phase-7, Wagholi

by M/s. Sharad Shree Enterprises, Sachin Date, Jayshree Date. Wagholi, Pune 412207. View on Google Maps

Launched
4 years promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
Bookings not reported
Price per sq ft (incl. balconies and terrace)
₹12,1002026 so far · 39 salesup 4% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK91
3 BHK101
Total units192
Buildings2
Land14.4 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: total units 177 → 192

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
820 – 850 sq ft₹97 lakh – ₹1.03 crore
1,130 sq ft₹1.31 – 1.39 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹11,600 per sq ft20 sales
2026 so farup 4% on 2025₹12,100 per sq ft39 sales

Rate vs other Wagholi projects, 2026: similar

Compared with 3 similar projects in PIN 412207

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 412207
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs4 yrs
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2028May 2029
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 10 months of the promised 4 years have passed
Concrete structure (RCC) 0% complete

Work not started as of Jul 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Majestique Towers East Phase-7 (MahaRERA P52100078306) is a residential project by M/s. Sharad Shree Enterprises, Sachin Date, Jayshree Date in Wagholi, Pune 412207. It was launched in December 2024. It has 192 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. 80% of the 2026 (so far) sales we found here were at ₹12,100 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size, based on 39 registered sales. Buyers here paid a rate similar to other Wagholi projects in 2026. Most buyers paid ₹97 lakh–₹1.03 crore for flats of 820–850 sq ft and ₹1.31–1.39 crore for 1,130 sq ft.

Majestique's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA74
Completed without extending the possession date35
Completed after an extension, or lapsed9
Under construction30
Possession date extended by the builder1
Typical time from launch to 100% structure3 years 8 months
Complaints on MahaRERA, all Majestique projects30 (11 of 74 projects)

See all Majestique projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078306.Check it on MahaRERA (P52100078306)All projects in Wagholi