Casagrand Caladium, Wagholi
by Casagrand Millenia Private Limited. Wagholi, Pune 412207. View on Google Maps
- Launched
- 4 years promised
- Possession date (MahaRERA)
- 2 years 7 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stageAverage across 5 buildings
- Units booked
- 92 of 33428% booked
- Price per sq ft (incl. balconies and terrace)
- ₹10,6002026 so far · 60 salesup 1% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 96 |
|---|---|
| 3 BHK | 238 |
| Total units | 334 |
| Buildings | 5 |
| Land | 2.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 61 → 92 · complaints 0 → 1
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 900 – 940 sq ft | ₹94 – 98 lakh |
| 1,290 – 1,300 sq ft | ₹1.35 – 1.41 crore |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2025 | ₹10,500 per sq ft | 27 sales |
|---|---|---|
| 2026 so farup 1% on 2025 | ₹10,600 per sq ft | 60 sales |
Rate vs other Wagholi projects, 2026: about 10% lower
Compared with 6 similar projects in PIN 412207
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs | 4 yrs 1 mth |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | May 2029 | March 2029 |
| Concrete structure (RCC) complete | 0% | 0% |
| Share of units booked | 28% | 51% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rohan Abhilasha 4 Phase 1 | April 2025 | June 2029 | 30% | 211 of 416 booked (51%) |
| Altamira by VTP Luxe Phase 1 | March 2025 | July 2030 | 0% | 338 of 479 booked (71%) |
| Kohinoor Riverdale - Phase II | February 2025 | December 2028 | 20% | 92 of 428 booked (21%) |
| Meander Wing D and E | August 2025 | December 2028 | 0% | Bookings not reported |
| Majestique Towers East Phase-7 | December 2024 | December 2028 | 0% | Bookings not reported |
| Mahindra IvyLush Tower C and Tower D | December 2024 | August 2030 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 92 | |
| 0% | 0% | 0% | 61 | |
| 0% | 0% | 0% | 4 |
"—" means MahaRERA shows no figure for that update.
About this project
Casagrand Caladium (MahaRERA P52100080302) is a residential project by Casagrand Millenia Private Limited in Wagholi, Pune 412207. It was launched in May 2025. It has 334 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is May 2029, unchanged since launch. Construction, averaged across its 5 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
92 of its 334 units are booked (28%). Since the December 2025 update, 31 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹10,600 per sq ft or less (up 1% on 2025), counting balconies and terrace in the size, based on 60 registered sales. Buyers here paid a rate about 10% lower than at other Wagholi projects in 2026. Most buyers paid ₹94–98 lakh for flats of 900–940 sq ft and ₹1.35–1.41 crore for 1,290–1,300 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.