Skip to main content
← Back

Parklane Urbanjoy Wing C, Sus

by Parklane Construction LLP. Sus, Pune 411021. View on Google Maps

Launched
3 years 8 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
47%Mid-construction
Units booked
88 of 14461% booked
Price per sq ft (incl. balconies and terrace)
₹8,3002026 so far · 29 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK2
2 BHK81
3 BHK61
Total units144
Buildings1
Land3.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 4% → 47% · total units 79 → 144

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
680 – 760 sq ft₹56 – 63 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹8,300 per sq ft26 sales
2026 so farabout the same as 2025₹8,300 per sq ft29 sales

Rate vs other Sus projects, 2026: similar

Compared with 5 similar projects in PIN 411021

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 8 mths4 yrs 6 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)December 2028June 2029
Concrete structure (RCC) complete47%0%
Share of units booked61%32%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 6 months of the promised 3 years 8 months have passed
Concrete structure (RCC) 47% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 95%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 4%Jul 2026: Concrete structure (RCC) 47%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 47%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%47%0%88
100%4%0%—
95%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Parklane Urbanjoy Wing C (MahaRERA P52100080095) is a residential project by Parklane Construction LLP in Sus, Pune 411021. It was launched in April 2025. It has 144 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 47% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

88 of its 144 units are booked (61%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 4% to 47%. 80% of the 2026 (so far) sales we found here were at ₹8,300 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 29 registered sales. Buyers here paid a rate similar to other Sus projects in 2026. Most buyers paid ₹56–63 lakh for flats of 680–760 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080095.Check it on MahaRERA (P52100080095)All projects in Bavdhan, Pashan, Sus