Serenity Home, Kondhwa Budruk

by Viren Buildcon LLP · Kondhwa Budruk, Pune 411048 · Map

Launched
Jul 20262 yrs 8 mths originally promised
Possession (MahaRERA)
Jul 2029Extended by 4 mths
Concrete structure
0%Early stage
Booked
6 of 3318%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
7
2 BHK
15
Other units
11
Total units
33
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹1.5 crore spent · latest estimate ₹5.8 crore · Oct 2026

Latest estimate ₹5.8 croreOct 2026: ₹1.5 crore1.5Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹1.5 crore

Compared with 6 similar projects in PIN 411048

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411048
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs 6 mths
Possession date extendedBy 4 mths4 of 6
Possession date (MahaRERA)Jul 2029Feb 2030
Concrete structure (RCC)0%0%
Units booked18%41%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Serenity Home by Viren Buildcon LLP is a 33-unit project in Kondhwa Budruk, Pune 411048, launched in July 2026 with possession due in July 2029. 6 units booked out of total 33 units. Work on the concrete structure (RCC) has not started.

Read full summary

Serenity Home is a project by Viren Buildcon LLP in Kondhwa Budruk, Pune 411048, registered with MahaRERA as PM1260002601281. It was launched in July 2026. It has 33 units in 2 buildings: 22 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2029, extended by 4 months from the original March 2029. Construction: excavation complete, structure (RCC) not started, final finishes not started.

6 units booked out of total 33 units (18%).