Sai Angan, Kondhwa Budruk

by Matoshri Developers · Kondhwa Budruk, Pune 411048 · Map

Launched
Jul 20262 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2029Extended by 4 mths
Concrete structure
0%Early stage
Booked
10 of 2540%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
24
Other units
1
Total units
25
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 411048

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411048
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths3 yrs 6 mths
Possession date extendedBy 4 mths4 of 6
Possession date (MahaRERA)Apr 2029Mar 2030
Concrete structure (RCC)0%0%
Units booked40%36%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sai Angan by Matoshri Developers is a 25-unit project in Kondhwa Budruk, Pune 411048, launched in July 2026 with possession due in April 2029. 10 units booked out of total 25 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sai Angan is a project by Matoshri Developers in Kondhwa Budruk, Pune 411048, registered with MahaRERA as PR1260002601306. It was launched in July 2026. It has 25 units in 1 building: 24 homes (1 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2029, extended by 4 months from the original December 2028. Construction: excavation not started, structure (RCC) not started, final finishes not started.

10 units booked out of total 25 units (40%).