Shiv Parvati Apartment, Kondhwa Budruk

by Shiv Parvati Developers · Kondhwa Budruk, Pune 411048 · Map

Launched
Jul 20264 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2031Extended by 4 mths
Concrete structure
25%Mid-construction
Booked
8 of 1650%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
4
2 BHK
12
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 411048

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411048
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths2 yrs 8 mths
Possession date extendedBy 4 mths4 of 6
Possession date (MahaRERA)Apr 2031Mar 2029
Concrete structure (RCC)25%0%
Units booked50%34%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Parvati Apartment by Shiv Parvati Developers is a 16-unit project in Kondhwa Budruk, Pune 411048, launched in July 2026 with possession due in April 2031. 8 units booked out of total 16 units. The concrete structure (RCC) is 25% complete.

Read full summary

Shiv Parvati Apartment is a project by Shiv Parvati Developers in Kondhwa Budruk, Pune 411048, registered with MahaRERA as PR1260002601322. It was launched in July 2026. It has 16 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2031, extended by 4 months from the original December 2030. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

8 units booked out of total 16 units (50%).