Skip to main content
← Back

Life Republic Sector R34/34TH Avenue-duet/phase - II, Jambhe

by Kolte-Patil Developers Limited. Jambhe, Pune 411033. View on Google Maps

Launched
5 years 4 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
3%Mid-constructionAverage across 3 buildings
Units booked
226 of 84327% booked
Price per sq ft (incl. balconies and terrace)
₹9,4002026 so far · 225 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK789
Other units (shops, offices or not given by type)54
Total units843
Buildings3
Land5.7 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: structure 0% → 3% · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
740 – 770 sq ft₹68 – 72 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹9,400 per sq ft225 sales

Rate vs other Jambhe projects, 2026: similar

Compared with 3 similar projects in PIN 411033

Projects with 350–1,600 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 4 mths5 yrs 1 mth
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2030December 2029
Concrete structure (RCC) complete3%0%
Share of units booked27%52%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 2 months of the promised 5 years 4 months have passed
Concrete structure (RCC) 3% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 3%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 3%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%3%0%226
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Life Republic Sector R34/34TH Avenue-duet/phase - II (MahaRERA PM1261012500469) is a residential project by Kolte-Patil Developers Limited in Jambhe, Pune 411033. It was launched in August 2025. It has 843 units in 3 buildings: 789 homes (2 BHK) and 54 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 3% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

226 of its 843 units are booked (27%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 3%. 80% of the 2026 (so far) sales we found here were at ₹9,400 per sq ft or less, counting balconies and terrace in the size, based on 225 registered sales. Buyers here paid a rate similar to other Jambhe projects in 2026. Most buyers paid ₹68–72 lakh for flats of 740–770 sq ft.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1261012500469.Check it on MahaRERA (PM1261012500469)All projects in Tathawade, Punawale, Jambhe