Skip to main content
← Back

Millennium Amara Phase 2, Mamurdi

by Millennium Developers. Mamurdi, Pune 412101. View on Google Maps

Launched
4 years 3 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
3%Mid-constructionAverage across 3 buildings
Units booked
38 of 14426% booked

Project facts

1 BHK6
2 BHK138
Total units144
Buildings3
Land2.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 0% → 3% · total units 44 → 144

Share on WhatsApp

Compared with 6 similar projects in PIN 412101

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 3 mths3 yrs 10 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)December 2029March 2030
Concrete structure (RCC) complete3%0%
Share of units booked26%7%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 1 month of the promised 4 years 3 months have passed
Concrete structure (RCC) 3% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 3%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 3%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%3%0%38
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Millennium Amara Phase 2 (MahaRERA PR1261012500899) is a residential project by Millennium Developers in Mamurdi, Pune 412101. It was launched in September 2025. It has 144 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 3% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

38 of its 144 units are booked (26%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 3%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1261012500899.Check it on MahaRERA (PR1261012500899)All projects in Kiwale, Ravet