Skip to main content
← Back

Kharadi New Project -Tower 5, Wagholi

Also known as Lodha Camelot

by Lodha Developers Limited. Wagholi, Pune 412207. View on Google Maps

Launched
4 years 2 months originally promised
Possession date (MahaRERA)
3 years 11 months awayExtended by 6 months (originally March 2030). Why possession dates change
Concrete structure (RCC)
0%Early stage
Units booked
Bookings not reported

Project facts

Other units (shops, offices or not given by type)4
Total units4
Buildings1
Land10 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: possession date March 2030 → September 2030

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
9 months of the originally promised 4 years 2 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 60%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 60%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
60%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Kharadi New Project -Tower 5 (MahaRERA PR1260002502039) is a residential project by Lodha Developers Limited in Wagholi, Pune 412207. It is also known as Lodha Camelot. It was launched in January 2026. It has 4 units, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2030, extended by 6 months from the original March 2030. Construction: excavation 60% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the possession date has moved from March 2030 to September 2030.

Lodha's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA56
Completed without extending the possession date15
Completed after an extension, or lapsed0
Under construction41
Possession date extended by the builder5
Typical time from launch to 100% structure3 years 7 months
Complaints on MahaRERA, all Lodha projects36 (17 of 56 projects)

See all Lodha projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1260002502039.Check it on MahaRERA (PR1260002502039)All projects in Wagholi