Aikyam, Ravet

by Urway Infra LLP. Ravet, Pune 412101. View on Google Maps

Launched
3 years 3 months originally promised
Possession date (MahaRERA)
3 years 5 months awayExtended by 1 year (originally March 2029). Why possession dates change
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
Bookings not reported
Price per sq ft (incl. balconies and terrace)
₹9,7002026 so far · 24 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK27
2 BHK128
3 BHK52
Total units207
Buildings3
Land3.1 acres
Landowner share16
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: possession date March 2029 → March 2030 · total units 42 → 207

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
760 – 810 sq ft₹74 – 79 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹9,700 per sq ft24 sales

Rate vs other Ravet projects, 2026: about 10% higher

Compared with 6 similar projects in PIN 412101

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 3 mths4 yrs 6 mths
Possession date extendedBy 1 year0 of 6
Possession date (MahaRERA)March 2030June 2030
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
10 months of the originally promised 3 years 3 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 27%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 27%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
27%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Aikyam (MahaRERA PM1260002501835) is a residential project by Urway Infra LLP in Ravet, Pune 412101. It was launched in December 2025. It has 207 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2030, extended by 1 year from the original March 2029. Construction, averaged across its 3 buildings: excavation 27% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the possession date has moved from March 2029 to March 2030. 80% of the 2026 (so far) sales we found here were at ₹9,700 per sq ft or less, counting balconies and terrace in the size, based on 24 registered sales. Buyers here paid a rate about 10% higher than at other Ravet projects in 2026. Most buyers paid ₹74–79 lakh for flats of 760–810 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002501835.Check it on MahaRERA (PM1260002501835)All projects in Kiwale, Ravet