Sandhu Palace, Bandra West

by Sandhu Builders · Bandra West, Mumbai 400050 · Map

Launched
Jul 2017First of 2 phases
Possession (MahaRERA)
Dec 2028Extended in 1 of 2 phases
Concrete structure
91%Weighted across 2 phases
Booked
–
Buildings
20.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
5
5+ BHK
35
Total units
40
Buildings
2
Land
0.3 acres
Phases
2
MahaRERA complaints
1

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Sandhu Palace A Wing
Completed
P5180000161035100%–
Sandhu Palace B Wing
Mid-construction
P51800001751527%0%
Show updates by phase

Sandhu Palace A Wing (P51800001610)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%25

"–" means MahaRERA shows no figure for that update.

Sandhu Palace B Wing (P51800001751)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%27%0%0
100%27%0%0
100%27%0%–
100%27%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)91%
Finishes, lifts and services88%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 91%Dec 2025: Concrete structure (RCC) 91%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 91%Dec 2024: Final finishes 88%Dec 2025: Final finishes 88%Jul 2026: Final finishes 88%Oct 2026: Final finishes 88%Excavation 100%Concrete structure (RCC) 91%Final finishes 88%

How to read construction stages

Compared with 4 similar projects in PIN 400050

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 5 mths6 yrs 7 mths
Possession date extendedYes3 of 4
Possession date (MahaRERA)Dec 2028Dec 2025
Concrete structure (RCC)91%33%
Units booked–0%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Sandhu Palace by Sandhu Builders is a 40-unit BMC-sanctioned project in Bandra West, Mumbai 400050, registered with MahaRERA in 2 phases, with possession due in December 2028. The concrete structure (RCC) is 91% complete.

Read full summary

Sandhu Palace is a BMC-sanctioned project by Sandhu Builders in Bandra West, Mumbai 400050, registered with MahaRERA as 2 phases (P51800001610, P51800001751). The first phase was launched in July 2017. Together the phases have 40 units in 2 buildings, with 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2028; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 91% complete and final finishes 88% complete. Neither phase has its structure complete.