Samyakth Bliss Tower B, Bandra West
by Samyakth Realties · Bandra West, Mumbai 400050 · Map
- Launched
- Aug 20176 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs 6 mths
- Concrete structure
- 36%Mid-construction
- Booked (free sale)
- 0 of 210% · 17 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 21 units
Rehab17 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 6
- 2 BHK
- 27
- 3 BHK
- 3
- Other units
- 2
- Total units
- 38
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 36% | 0% | 0 | |
| 100% | 36% | 0% | – | |
| 100% | 36% | 0% | – | |
| 100% | 28% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400050
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 10 mths | 5 yrs 10 mths |
| Possession date extended | By 2 yrs 6 mths | 3 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2026 |
| Concrete structure (RCC) | 36% | 48% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Residency, Bandra West
- White House, Bandra West
- Marina, Bandra West
- Sandhu Palace, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Residency | August 2017 | December 2022 | 0% | – |
| White House | August 2017 | June 2027 | 30% | 0 units booked out of 16 units for sale |
| Marina | August 2017 | December 2024 | 67% | 60 units booked out of total 62 units |
| Sandhu Palace | July 2017 | Dec 2028 | 91% | – |
About this project
Samyakth Bliss Tower B by Samyakth Realties is a 38-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in August 2017 with possession due in December 2026. 0 units booked out of 21 units for sale. The concrete structure (RCC) is 36% complete.
Read full summary
Samyakth Bliss Tower B is a BMC-sanctioned project by Samyakth Realties in Bandra West, Mumbai 400050, registered with MahaRERA as P51800008134. It was launched in August 2017. It has 38 units in 1 building: 36 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 21 are for sale and 17 are rehab units for existing members.
Its registered possession date is December 2026, extended by 2 years 6 months from the original June 2024. Construction: excavation complete, structure (RCC) 36% complete, final finishes not started.
0 units booked out of 21 units for sale (0%).