- Launched
- Aug 20175 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2022Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 2
- 3 BHK
- 30
- Other units
- 4
- Total units
- 36
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400050
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 6 yrs 4 mths |
| Possession date extended | No | 4 of 5 |
| Possession date (MahaRERA) | Dec 2022 | Dec 2026 |
| Concrete structure (RCC) | 0% | 67% |
| Units booked | – | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- White House, Bandra West
- Samyakth Bliss Tower B, Bandra West
- Epitome, Bandra West
- Marina, Bandra West
- Sandhu Palace, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| White House | August 2017 | June 2027 | 30% | 0 units booked out of 16 units for sale |
| Samyakth Bliss Tower B | August 2017 | December 2026 | 36% | 0 units booked out of 21 units for sale |
| Epitome | August 2017 | December 2019 | 70% | – |
| Marina | August 2017 | December 2024 | 67% | 60 units booked out of total 62 units |
| Sandhu Palace | July 2017 | Dec 2028 | 91% | – |
About this project
Residency by Zoy Shelcon Private Limited is a 36-unit project in Bandra West, Mumbai 400050, launched in August 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.
Read full summary
Residency is a project by Zoy Shelcon Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as P51800005977. It was launched in August 2017. It has 36 units in 1 building: 32 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.