- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Jun 2022 – May 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 97
- 3 BHK
- 20
- Total units
- 117
- Buildings
- 2
- Land
- 0.9 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| The Golf Boulevard Building - 1 Early stage Lapsed | P51800002734 | 59 | 0% | – | |
| The Golf Boulevard Building 2 Early stage Lapsed | P51800021401 | 58 | 0% | – |
Show updates by phase
The Golf Boulevard Building - 1 (P51800002734)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 85% | 0% | 0% | – | |
| 85% | 0% | 0% | – | |
| 85% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
The Golf Boulevard Building 2 (P51800021401)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400071
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | No | 5 of 6 |
| Possession date (MahaRERA) | Jun 2022 – May 2025 | May 2022 |
| Concrete structure (RCC) | 0% | 84% |
| MahaRERA complaints (filed by or against the builder) | 0 | 11 |
The 6 projects
- Poddar Spraha Diamond Phase-I, Chembur
- Odina, Chembur
- Rite Skyluxe, Chembur
- Zynergy, Chembur
- Safal Sai And Safal Sainath, Chembur
- Ruparel Orion, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Poddar Spraha Diamond Phase-I | August 2017 | September 2022 | 100% | 115 units booked out of total 118 units |
| Odina | August 2017 | March 2020 | 100% | – |
| Rite Skyluxe | August 2017 | December 2020 | 94% | – |
| Zynergy | August 2017 | November 2024 | 24% | – |
| Safal Sai And Safal Sainath | August 2017 | October 2026 | 63% | 145 units booked out of 193 units for sale |
| Ruparel Orion | August 2017 | December 2021 | 75% | – |
About this project
The Golf Boulevard by Empress & Adishakti Jv is a 117-unit project in Chembur, Mumbai 400071, registered with MahaRERA in 2 phases, with possession dates from June 2022 to May 2025. Work on the concrete structure (RCC) has not started.
Read full summary
The Golf Boulevard is a project by Empress & Adishakti Jv in Chembur, Mumbai 400071, registered with MahaRERA as 2 phases (P51800002734, P51800021401). The first phase was launched in August 2017. Together the phases have 117 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The phases' registered possession dates run from June 2022 to May 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. Neither phase has its structure complete.