Safal Sai And Safal Sainath, Chembur
Lapsed
by Mangalnath Developers Pvt Ltd · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 2 yrs 10 mthsWhat does Lapsed mean?
- Concrete structure
- 63%Mid-construction
- Booked (free sale)
- 145 of 19375% · 5 rehab units
- Buildings
- 21.2 acres
- MahaRERA complaints
- 11Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale145 booked out of 193 units
Rehab5 units for existing members
Total 198 units. Rehab units are not for sale.
Project facts
- 1 RK
- 12
- 1 BHK
- 125
- 2 BHK
- 58
- Other units
- 3
- Total units
- 198
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 11
- Free-sale units
- 193
- Rehab units
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 63% | 50% | 145 | |
| 100% | 63% | 50% | 145 | |
| 100% | 63% | 38% | 138 | |
| 100% | 63% | 38% | 124 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 4 yrs 10 mths |
| Possession date extended | By 2 yrs 10 mths | 3 of 6 |
| Possession date (MahaRERA) | Oct 2026 | Jul 2022 |
| Concrete structure (RCC) | 63% | 88% |
| Units booked (free sale) | 75% | 97% |
| MahaRERA complaints (filed by or against the builder) | 11 | 2 |
The 6 projects
- Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71, Chembur
- Zynergy, Chembur
- Ruparel Orion, Chembur
- Safal Trademark, Chembur
- Poddar Spraha Diamond Phase-I, Chembur
- The Golf Boulevard, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 | August 2017 | January 2021 | 100% | 204 units booked out of total 209 units |
| Zynergy | August 2017 | November 2024 | 24% | – |
| Ruparel Orion | August 2017 | December 2021 | 75% | – |
| Safal Trademark | August 2017 | April 2027 | 100% | 212 units booked out of 230 units for sale |
| Poddar Spraha Diamond Phase-I | August 2017 | September 2022 | 100% | 115 units booked out of total 118 units |
| The Golf Boulevard | August 2017 | Jun 2022 – May 2025 | 0% | – |
About this project
Safal Sai And Safal Sainath by Mangalnath Developers Pvt Ltd is a 198-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 145 units booked out of 193 units for sale. The concrete structure (RCC) is 63% complete.
Read full summary
Safal Sai And Safal Sainath is an SRA-sanctioned project by Mangalnath Developers Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800009799. It was launched in August 2017. It has 198 units in 2 buildings: 195 homes (1 RK, 1 BHK and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 198 units, 193 are for sale and 5 are rehab units for existing members.
Its registered possession date is October 2026, extended by 2 years 10 months from the original December 2023. Construction: excavation complete, structure (RCC) 63% complete, final finishes 50% complete.
145 units booked out of 193 units for sale (75%).