- Launched
- Aug 20174 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2021Not extendedWhat does Lapsed mean?
- Concrete structure
- 75%Mid-construction
- Booked
- –
- Buildings
- 21.7 acres
- MahaRERA complaints
- 45Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 96
- 2 BHK
- 75
- 3 BHK
- 48
- Other units
- 4
- Total units
- 223
- Buildings
- 2
- Land
- 1.7 acres
- Phases
- 1
- MahaRERA complaints
- 45
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 97% | 75% | 0% | – | |
| 97% | 75% | 0% | – | |
| 97% | 75% | 0% | 218 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 5 yrs 10 mths |
| Possession date extended | No | 4 of 6 |
| Possession date (MahaRERA) | Dec 2021 | Nov 2025 |
| Concrete structure (RCC) | 75% | 82% |
| Units booked | – | 92% |
| MahaRERA complaints (filed by or against the builder) | 45 | 2 |
The 6 projects
- Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71, Chembur
- Safal Sai And Safal Sainath, Chembur
- Safal Trademark, Chembur
- Zynergy, Chembur
- One Meraki, Chembur
- The Golf Boulevard, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 | August 2017 | January 2021 | 100% | 204 units booked out of total 209 units |
| Safal Sai And Safal Sainath | August 2017 | October 2026 | 63% | 145 units booked out of 193 units for sale |
| Safal Trademark | August 2017 | April 2027 | 100% | 212 units booked out of 230 units for sale |
| Zynergy | August 2017 | November 2024 | 24% | – |
| One Meraki | August 2017 | Dec 2026 | 100% | – |
| The Golf Boulevard | August 2017 | Jun 2022 – May 2025 | 0% | – |
About this project
Ruparel Orion by K D Lite Developers Pvt Ltd (Ruparel) is a 223-unit project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 75% complete.
Read full summary
Ruparel Orion is a project by K D Lite Developers Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800004525. It was launched in August 2017. It has 223 units in 2 buildings: 219 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021. That date has passed and no extension has been recorded. Construction: excavation 97% complete, structure (RCC) 75% complete, final finishes not started.
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.