Poddar Spraha Diamond Phase-I, Chembur

Lapsed

by Poddar Housing and Development Limited · Chembur, Mumbai 400071 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Sep 2022Extended by 9 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
115 of 11897%
Buildings
20.4 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
60
2 BHK
58
Total units
118
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services53%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 53%Dec 2025: Final finishes 53%Jul 2026: Final finishes 53%Oct 2026: Final finishes 53%Excavation 100%Concrete structure (RCC) 100%Final finishes 53%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%53%115
100%100%53%–
100%100%53%–
100%100%53%115

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths4 yrs 4 mths
Possession date extendedBy 9 mths4 of 6
Possession date (MahaRERA)Sep 2022Sep 2021
Concrete structure (RCC)100%78%
MahaRERA complaints (filed by or against the builder)36

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Poddar Spraha Diamond Phase-I by Poddar Housing and Development Limited is a 118-unit project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 115 units booked out of total 118 units. The concrete structure (RCC) is complete.

Read full summary

Poddar Spraha Diamond Phase-I is a project by Poddar Housing and Development Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51900002986. It was launched in August 2017. It has 118 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2022, after an extension of 9 months from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 53% complete.

115 units booked out of total 118 units (97%).