Shree Ganesh Chs, Ghatkopar West

Lapsed

by Shree Saibaba Constructions Private Limited · Ghatkopar West, Mumbai 400086 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 4 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
3 of 388%
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
10
2 BHK
19
3 BHK
9
Total units
38
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 27%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%3
100%100%80%–
100%100%80%–
100%27%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400086

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400086
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 4 mths
Possession date extendedBy 4 yrs4 of 4
Possession date (MahaRERA)Jun 2025Mar 2023
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Shree Ganesh Chs by Shree Saibaba Constructions Private Limited is a 38-unit project in Ghatkopar West, Mumbai 400086, launched in August 2017; its MahaRERA registration has lapsed. 3 units booked out of total 38 units. The concrete structure (RCC) is complete.

Read full summary

Shree Ganesh Chs is a project by Shree Saibaba Constructions Private Limited in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800006301. It was launched in August 2017. It has 38 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 4 years from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

3 units booked out of total 38 units (8%).