Vighneshwar Cooperative Housing Society Limited, Ghatkopar West
by Vighneshwar Coop Housing Society Limited · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Sep 20173 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 6 yrs 3 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 40 of 5277% · 39 in Jul 2026
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 4
- 2 BHK
- 45
- 3 BHK
- 2
- Other units
- 1
- Total units
- 52
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 40 | |
| 100% | 100% | 25% | 39 | |
| 100% | 75% | 0% | 39 | |
| 100% | 75% | 0% | 24 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400086
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 3 yrs 5 mths |
| Possession date extended | By 6 yrs 3 mths | 5 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Sep 2023 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 77% | 8% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Avis Vraj A Paradise, Ghatkopar West
- Shree Ganesh Chs, Ghatkopar West
- Shree Shambhav Darshan, Ghatkopar West
- Anchor Residency, Ghatkopar West
- Arihant Heights, Ghatkopar West
- Vikram Delite CHSL, Ghatkopar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Avis Vraj A Paradise | September 2017 | December 2020 | 100% | – |
| Shree Ganesh Chs | August 2017 | June 2025 | 100% | 3 units booked out of total 38 units |
| Shree Shambhav Darshan | August 2017 | December 2021 | 50% | – |
| Anchor Residency | July 2017 | December 2021 | 100% | – |
| Arihant Heights | January 2018 | December 2026 | 100% | 47 units booked out of total 104 units |
| Vikram Delite CHSL | July 2018 | December 2028 | 100% | 0 units booked out of 42 units for sale |
About this project
Vighneshwar Cooperative Housing Society Limited by Vighneshwar Coop Housing Society Limited is a 52-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in September 2017 with possession due in April 2027. 40 units booked out of total 52 units. The concrete structure (RCC) is complete.
Read full summary
Vighneshwar Cooperative Housing Society Limited is a BMC-sanctioned project by Vighneshwar Coop Housing Society Limited in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800012941. It was launched in September 2017. It has 52 units in 1 building: 51 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 6 years 3 months from the original January 2021. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.
40 units booked out of total 52 units (77%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2025 to April 2027.